36. Where alternative technical proposals are possible, the bidding process used is
(A) single stage one envelope procedure
(B) single stage two envelope procedure
(C) two stage bidding procedure
(D) two stage two envelope bidding procedure
37. Where the bids are to be evaluated on technical and financial grounds and price is taken into account after technical evaluation, the bidding process used is
(A) single stage one envelope procedure
(B) single stage two envelope procedure
(C) two stage bidding procedure
(D) two stage two envelope bidding procedure
38. In large and complex contracts where technically unequal proposals are likely to be encountered, or there are two or more equally acceptable technical solutions available to the procuring agency, the bidding process used is
(A) single stage one envelope procedure
(B) single stage two envelope procedure
(C) two stage bidding procedure
(D) two stage two envelope bidding procedure
39. Any bidder feeling aggrieved by any act of the procuring agency may lodge a written complaint concerning his grievances not later than _______ days after the announcement of the bid evaluation report.
(A) 7
(B) 10
(C) 15
(D) 30
40. The committee shall investigate and decide upon the complaint within _______ days of the receipt of the complaint.
(A) 15
(B) 30
(C) 45
(D) 60
ANSWERS: PUBLIC PROCUREMENT
36(D) 37(B) 38(C) 39(C) 40(A)